The CPP3 project is the single largest investment in history of ALMARAI ‘’The Central Processing Plant is considered the heart of Almarai’s operations’’.
WETICO’s scope of work was to design and build a RO Water Treatment Plant utilizing raw well water grey water (as Feed water) so that it can be transformed to filtered Water for Production, cleaning, and other purposes.
TECHNICAL INFORMATION
Treatment System
1. Ultra-Filtration
2. Self-Cleaning Tekleen Filtration
3. Reverse Osmosis
4. General water treatment chemical dosing
5. Chlorine dioxide Dosing (CLO2)
6. SCADA systems
Capacity
3 x 1000 M3/day Ingredient RO plants
3 x 667 M3/day Reuse RO plants
Scope
Design, Procurement, Fabrication, Supply,
Installation, Testing and Commissioning.