Sewage Treatment Plant located at a very prestigious technology Center in Riyadh with an average capacity of 2000CMD.

Information Technology & Communication Complex project is for treating the sewage water that comes from the different facilities in the complex.

The sewage treatment plant of average capacity of 2000 m3/day and can be extended to 6000 m3/day at peak flow. WETICO’s role was to design, supply, install, test, and commission the sewage treatment plant.

TECHNICAL INFORMATION

Treatment System

Primary treatment, biological activated sludge treatment, tertiary filtration, & chemical disinfection.

Capacity

2000 m3/day

Scope

Design, engineering, manufacturing, erection, factory testing, packing, Shipping& supply, installation, site testing & site training.